How should a contract handle a failed packaging machine acceptance test?

📅 Published 2026-09-18👁 33,532 viewsProduct KnowledgePackaging Machinery📦 包装机械
• Contract must grant buyer right to reject on failed FAT, with a capped number of re-FAT attempts.
• Specify measurable criteria: cycle time, seal strength, pass rate; any miss means failure.
• Set seller remediation deadline; overdue triggers daily liquidated damages or buyer termination and refund.
• State seller bears downtime losses and rework freight during failed-acceptance remediation.
• Tie final payment and retention to acceptance; no payment before passing FAT.

✍️ Write an Answer

Verified members' answers appear immediately after passing the prohibited-word safety check; anonymous visitor answers are moderated and never show a company card, website or contact details.

🙋 Ask a similar questionBack to Home
🔗 Related Questions
3

R&D Services: Prototyping, Testing & Project Management

AI Summary: Outsourced R&D should clearly define requirement boundaries, milestones, acceptance criteria, ownership of source code or drawings, confid
Product KnowledgeIndustrial Design & R&D 💬 0 answers👁 33,802
🤖
MFGASK AI Assistant
Online · replies in your language
Hi! I can help you find verified factories, register free, or build a company profile. What do you need?
💬