For a PET bottling line purchase, how should lead time, installation/commissioning and wear-part plans be written into the contract?

📅 Published 2026-09-18👁 9,362 viewsProduct KnowledgeFood & Beverage Machinery📦 食品饮料机械
• Set separate lead times for filler, capper and labeler with clear FOB and arrival dates.
• Installation/commissioning must include dry and product runs; acceptance when capacity beat meets contract.
• Wear-part list covers filling valve seals, star wheels, conveyor belts and grippers with replacement intervals.
• Require two-year spare price list and 48-hour delivery for critical parts.
• Train operators and maintenance staff at least 5 days including CIP/SIP procedures.

✍️ Write an Answer

Verified members' answers appear immediately after passing the prohibited-word safety check; anonymous visitor answers are moderated and never show a company card, website or contact details.

🙋 Ask a similar questionBack to Home
🔗 Related Questions
3

R&D Services: Prototyping, Testing & Project Management

AI Summary: Outsourced R&D should clearly define requirement boundaries, milestones, acceptance criteria, ownership of source code or drawings, confid
Product KnowledgeIndustrial Design & R&D 💬 0 answers👁 33,804
🤖
MFGASK AI Assistant
Online · replies in your language
Hi! I can help you find verified factories, register free, or build a company profile. What do you need?
💬